Paper Mill 3MW Co-Gen Installation - Coolaroo Victoria

Industry: Pulp & Paper Industry
Category:Electrification, Project Management, Instrumentation
Services:Cable / Ladder Tray Installation, Cable Installation and Termination

Description: Project requirements -  electrification installation & commissioning of a newly installed steam turbine generation unit and its associated equipment comprising boiler, fuel handling, feed pump, MCC Room, turbine & generator controls.

Works included - Integration with Woodward synchronisation control and Bently Nevada vibration monitoring system including complete MCC fit out and installation of power distribution, VESDA, Purfil Systems, UPS, ABB AC800 DCS, ACS800 & ACS355 VSD's, Siemens turbine/generator set control, HV switchgear & engineering station, instrumentation and commissioning.

Duration: 12 months
Staff: 25
I/O count: 400